Okay people....I called POP and got the scoop. This is the order of the renovations.
60s era (bldgs 4, 5) - started but not finished and not currently renovating this era
70s era (bldgs 6, 10) - 95-100% complete
80s era (bldgs 7, 9) - 95-100% complete
90s era (bldg 8) - starting now
50s era (bldgs 1, 2, 3)- scheduled start date August 23, scheduled end date 1st week of November
60s era (bldgs 4,5) - phase 2 - finish the 60s building to start after the 50s is complete
She said they are doing one floor at a time and don't start another floor until the current one is complete. Because of the summer months being so "packed" they will be slowing down for the season. (if they were packed, why so many promotions????) She said this is the "contract", but things could slow down or speed up at any time.
So....I like the 50s building and they are starting those 1 week before I get there...UGH. She said if you want a renovated room, you can request it 10 days before you arrive - although I assume that is just a "request". So, now that I don't have to stress about
Free Dining anymore, I guess I'll stress about Pop's renovations! We will stay in the 50s building regardless (it's our favorite) - but it would be nice to be in a renovated room.