I thought I'd post this to try and keep everyone up to date. I will update as I hear from other folks:
This is the original conversion schedule. The bold is the actual:
Loop 900 – closed 7/08 to 7/25 – reopens 7/26/08. - Complete
Loop 1000 – closed 7/27 to 8/08 – reopens 8/09/08. - Complete
Loop 1100 – closed 8/10 to 8/22 – reopens 8/23/08. - Complete
Loop 500 – closed 8/24 to 9/21 – reopens 9/22/08. - Complete
Loop 800 – closed 9/22 to 11/01 – reopens 11/02/08. - Complete
Loop 400 – closed 11/03 to 11/21 – reopens 11/22/08. - Complete
Loop 600 – closed 11/30 to 12/19 – reopens 12/20/08. - Existing sites completed,
Expansion Complete
Loop 1300 – closed 1/4 to 1/23 – reopens 1/24/09. - Complete, done early
Loop 1200 – closed 1/25 to 2/06 – reopens 2/07/09. - Complete, done early
Loop 1400 – closed 2/08 to 2/13 – reopens 2/14/09. - Complete
Loop 700 – closed 3/15 to 4/03 – reopens 4/04/09. - Open Again after 2nd Round of Work
Loop 1500 and 2000 - Cable install complete
Loop 1600, 1700, 1800, and 1900 Cable install complete
No changes made at all to 100, 200, and 300
UNLESS THEY CLOSE ANOTHER LOOP DOWN AFTER THE 4th HOLIDAY, THE FORT CONVERSION MAY BE COMPLETE
This is the original conversion schedule. The bold is the actual:
Loop 900 – closed 7/08 to 7/25 – reopens 7/26/08. - Complete
Loop 1000 – closed 7/27 to 8/08 – reopens 8/09/08. - Complete
Loop 1100 – closed 8/10 to 8/22 – reopens 8/23/08. - Complete
Loop 500 – closed 8/24 to 9/21 – reopens 9/22/08. - Complete
Loop 800 – closed 9/22 to 11/01 – reopens 11/02/08. - Complete
Loop 400 – closed 11/03 to 11/21 – reopens 11/22/08. - Complete
Loop 600 – closed 11/30 to 12/19 – reopens 12/20/08. - Existing sites completed,
Expansion Complete
Loop 1300 – closed 1/4 to 1/23 – reopens 1/24/09. - Complete, done early
Loop 1200 – closed 1/25 to 2/06 – reopens 2/07/09. - Complete, done early
Loop 1400 – closed 2/08 to 2/13 – reopens 2/14/09. - Complete
Loop 700 – closed 3/15 to 4/03 – reopens 4/04/09. - Open Again after 2nd Round of Work
Loop 1500 and 2000 - Cable install complete
Loop 1600, 1700, 1800, and 1900 Cable install complete
No changes made at all to 100, 200, and 300
UNLESS THEY CLOSE ANOTHER LOOP DOWN AFTER THE 4th HOLIDAY, THE FORT CONVERSION MAY BE COMPLETE