deedeetoo
DIS Veteran
- Joined
- May 8, 2003
- Messages
- 1,874
We just had our kitchen remodeled. It was a big job involving moving walls, windows and plumbing, in addition to the standard new cabinets, counter, appliances, backsplash etc. It is almost done. The one thing that is missing is a piece of trim that goes along the top of the cabinets in one section.
So here is the story with the trim - the designer initially didn't quite order enough. This is custom trim and there were three pieces missing from the initial order. The contractor discovered that he was short right before Christmas. The factory where they produce the cabinets and trim was shut down for two weeks for Christmas so the new sections didn't get ordered until early January. The box arrived at the designer's in late January, who gave it to the contractor, who said it only contained 2 of 3 missing pieces. We don't know whose mistake this is. The factory claimed they shipped all three pieces, the contractor claims it wasn't there. The designer re-ordered the now one missing section. It has not come in yet. Designer says soon, but last time soon took two weeks.
So the contractor says that since the work is substantially done, he wants final payment but to hold back $500. Our contract says final payment is due upon completion. The job is not complete. There is a fairly obvious section of cabinet in our very expensive (to us) kitchen that has a whole above it. We are debating what to do. Is $500 enough to hold back? Should we hold back more? The entire amount we still owe is $3885 which seems like too much to hold back at this point. We have no reason not to trust the contractor, but still you here horror stories of them not ever finishing and this is a very obvious section to an otherwise beautiful kitchen. Any advice on what to do?
So here is the story with the trim - the designer initially didn't quite order enough. This is custom trim and there were three pieces missing from the initial order. The contractor discovered that he was short right before Christmas. The factory where they produce the cabinets and trim was shut down for two weeks for Christmas so the new sections didn't get ordered until early January. The box arrived at the designer's in late January, who gave it to the contractor, who said it only contained 2 of 3 missing pieces. We don't know whose mistake this is. The factory claimed they shipped all three pieces, the contractor claims it wasn't there. The designer re-ordered the now one missing section. It has not come in yet. Designer says soon, but last time soon took two weeks.
So the contractor says that since the work is substantially done, he wants final payment but to hold back $500. Our contract says final payment is due upon completion. The job is not complete. There is a fairly obvious section of cabinet in our very expensive (to us) kitchen that has a whole above it. We are debating what to do. Is $500 enough to hold back? Should we hold back more? The entire amount we still owe is $3885 which seems like too much to hold back at this point. We have no reason not to trust the contractor, but still you here horror stories of them not ever finishing and this is a very obvious section to an otherwise beautiful kitchen. Any advice on what to do?