Latest parking lot/entrance reconfiguration work from the sky courtesy of user
@bioreconstruct on X.
Link here.
Lines added by me and are approximate.
A lot going on with this project and still a long way to go. At left, ongoing Floridian Way widening (to four lanes) and reconfiguration). A traffic circle will eventually be in approximately the larger red circle area.
For the new Poly entrance, if you zoom in you can see concrete has been poured for the new security guard house (outlined in red), and you can start to see the outline of what will be the new guest entrance roadway (outlined in yellow).
The current Poly entrance will eventually be bus only, with additional bus stops and a turnaround added - generally the red outline.
Seems like the phasing of the work is to get the new guest entrance complete then they'll move on to the old entrance/bus area. Still a ways to go here with the Floridian Way traffic circle and Seven Seas Drive eventually being re-routed/re-configured partially through the CM parking area to intersect with the traffic circle.
Plans from the stormwater permits also attached for reference.