I decided I would start a separate thread for remodeling phase 2. First, i wanted to be able to find my posts easily as i tend to chronicle the remodel better on the boards and then i show other people. Second because this will also entail us camping while phase 2 is going on. This will hopefully tackle all of it.
First let's talk background. Last year we remodeled the master bath. We did major changes to it. Removed the tub, shifted the shower to where the tub was. Where the shower was we moved our stackable washer and dryer from a tiny room off the kitchen to where the shower was. The bathroom remodel was awesome. We love it. We also love that the old laundry room is now a pantry for the kitchen.
With the laundry moved we could now start phase 2. This will tackle two major things. First we will replace the floors in the the two bedrooms, entry way, living room, kitchen and tiny laundry room with tile floor. The bedrooms are currently carpet and the other floor is hardwood. The second part of the remodel is replacing all the cabinets in the kitchen including counter top and sink. We will also have the laundry room converted to a pantry with counter top and shelves.
All this work will have us living in the RV up in Blairsville for i am guessing 10 weeks. The contractor said 6 to 8 weeks so i am planning 10 to 12 weeks. We have tried to make it easier on them by moving all our furniture out. We have spend the last two weekends moving stuff. i am so sore. This coming weekend we setup in Blairsville.
Next post will contain the before pictures (but after furniture has been moved out).
First let's talk background. Last year we remodeled the master bath. We did major changes to it. Removed the tub, shifted the shower to where the tub was. Where the shower was we moved our stackable washer and dryer from a tiny room off the kitchen to where the shower was. The bathroom remodel was awesome. We love it. We also love that the old laundry room is now a pantry for the kitchen.
With the laundry moved we could now start phase 2. This will tackle two major things. First we will replace the floors in the the two bedrooms, entry way, living room, kitchen and tiny laundry room with tile floor. The bedrooms are currently carpet and the other floor is hardwood. The second part of the remodel is replacing all the cabinets in the kitchen including counter top and sink. We will also have the laundry room converted to a pantry with counter top and shelves.
All this work will have us living in the RV up in Blairsville for i am guessing 10 weeks. The contractor said 6 to 8 weeks so i am planning 10 to 12 weeks. We have tried to make it easier on them by moving all our furniture out. We have spend the last two weekends moving stuff. i am so sore. This coming weekend we setup in Blairsville.
Next post will contain the before pictures (but after furniture has been moved out).