Not sure if you've seen this tentative schedule:
Magnolia Bend, Acadian House: starts 26 June 2011, for approx. six weeks
Magnolia Bend, Magnolia Terrace: starts 31 July 2011, for approx. six weeks
Alligator Bayou, Lodges 36, 37, 38, 39: starts 25 October 2011, for approx. eight weeks
Magnolia Bend, Oak Manor: starts 15 January 2012, for approx. five weeks [Royal Themed Rooms]
Magnolia Bend, Parterre Place: starts 19 February 2012, for approx. five weeks [Royal Themed Rooms]
Alligator Bayou, Lodges 24, 16, 17, 28: starts 3 April 2012, for approx. eight weeks
Alligator Bayou, Lodges 14, 27, 18, 15: starts 8 May 2012, for approx. seven weeks
Alligator Bayou, Lodges 25, 35, 26, 34: starts 5 June 2012, for approx. eight weeks
It looks like they should be done with Acadian House and Magnolia Terrace by the time of your trip and no other work appears to be scheduled during the month of September.