curious to know the schedule of room progress
we arrive 3/31 for a preferred room!!
This schedule is not concrete since they have been a tad bit ahead of schedule. Borrowed from
The following dates include some overlap between buildings, and are obviously always going to be SUBJECT TO CHANGE, so please don't make your wedding plans based on them! I have deliberately not quoted the planned completion dates to avoid anyone getting disappointed.
Magnolia Bend, Acadian House: starts 26 June 2011, for approx. six weeks
Magnolia Bend, Magnolia Terrace: starts 31 July 2011, for approx. six weeks
Alligator Bayou, Lodges 36, 37, 38, 39: starts 25 October 2011, for approx. eight weeks
Magnolia Bend, Oak Manor: starts 15 January 2012, for approx. five weeks [Royal Themed Rooms]
Magnolia Bend, Parterre Place: starts 19 February 2012, for approx. five weeks [Royal Themed Rooms]
Alligator Bayou, Lodges 24, 16, 17, 28: starts 3 April 2012, for approx. eight weeks
Alligator Bayou, Lodges 14, 27, 18, 15: starts 8 May 2012, for approx. seven weeks
Alligator Bayou, Lodges 25, 35, 26, 34: starts 5 June 2012, for approx. eight weeks
The construction work will happen one building at a time, however especially in Alligator Bayou it looks as though work on the next lodge may well commence before the previous one has been fully completed, giving some overlap where two buildings could be out of use at the same time.
I have no idea why the schedule for the two mansion buildings which are due for the 'Royal' treatment (Oak Manor and Parterre Place) is slightly shorter than the other two buildings - you'd have thought they would actually take longer to complete. Time will tell I guess.