I spoke with the front desk manager about the renovations scheduled for OKW this year. Here is what he had for me.
95% hard surface replacement. That is what it is going to be. He didn't say which 5% was not being replaced, but I'm going to guess itls the wall plaster.
It was supposed to be a 100% hard surface replacement with members paying for 95% and the hotel paying for 5%, but legal told them "no", members need to pay for all of it. That is why there is only going to be a 95% of hard surface replacement. Evidently they know how much they have from dues etc to cover this.
Floors! He said the actual flooring material has not yet been determined. It MIGHT be hard wood and it MIGHT be laminate, but if it's laminate, they plan to use a sound barrier under it. There will also be stone counters both on the cabinets and the island. They don't even have a model done up yet, because not allo design decisions have been made. He assured me they would indeed try to hold true to theme.
When are interior renovations starting? This one threw me for a loop. They aren't actually scheduled to start yet, but his best guess is it wont be until at least July!!!! They need to have as many units open for the summer as possible, so they wont start taking buildings out of service during those high use times.
I was right about what is currently going on at buildings 63 and 64. That is the last of the exterior renovations that have been taking place for the past year and a half. I suspect that means that the interior renovations will follow the same pattern of buildings when that gets started as well. Stay tuned!
95% hard surface replacement. That is what it is going to be. He didn't say which 5% was not being replaced, but I'm going to guess itls the wall plaster.
It was supposed to be a 100% hard surface replacement with members paying for 95% and the hotel paying for 5%, but legal told them "no", members need to pay for all of it. That is why there is only going to be a 95% of hard surface replacement. Evidently they know how much they have from dues etc to cover this.
Floors! He said the actual flooring material has not yet been determined. It MIGHT be hard wood and it MIGHT be laminate, but if it's laminate, they plan to use a sound barrier under it. There will also be stone counters both on the cabinets and the island. They don't even have a model done up yet, because not allo design decisions have been made. He assured me they would indeed try to hold true to theme.
When are interior renovations starting? This one threw me for a loop. They aren't actually scheduled to start yet, but his best guess is it wont be until at least July!!!! They need to have as many units open for the summer as possible, so they wont start taking buildings out of service during those high use times.
I was right about what is currently going on at buildings 63 and 64. That is the last of the exterior renovations that have been taking place for the past year and a half. I suspect that means that the interior renovations will follow the same pattern of buildings when that gets started as well. Stay tuned!