I think they have the 4th and 5th floor of the main building already well under way. If you look back through the threads, you’ll see that they didn’t actually block off the small side of the building until well after the first signs of construction back in August. For a good month, there was some construction noise and plastic down in the main building, 4th and 5th floor, but that was it.
When we were there in mid-September, there was zero activity on the side they’ve completed. I’d estimate they are actually taking 4 to 6 weeks total per room to do the remodel. There’s a very good chance, now that they are rolling and have their materials and work sequenced, that they will flip them faster.