Good morning All -
I read a note from another poster that questions were brought up to the CM recently during the Lodge Tour and here are the answers.
1 - There is NO Zero Entry Pool modification. The main pool will continue to have the same footprint AND water capacity. The main pool will recieve a new exterior coating that will advance to 4' from the pool (pool deck) for reduced chances of slipping, etc. Therefore, the main pool will remain the same except for a new and improved coating of the pool and the immediate pool deck area.
2 - A Kids Splash Zone with dumping buckets is being built in the area in which you see most of the construction taking place. (Please see recent Grand Floridian Kid Play Area). The footprint here is enlarged (as you can see from the pics) as the kiddie pool area has been removed.
3 - The whirlpool area is apparantly going to be ADA accessible. It would appear from earlier pics that the wooden walkway behind the pool (and in front of the geyser) has been pulled up for piping / routing etc. and if this will be ADA, then I expect a ramp or similar to be made near the pool deck area.
4 - The seating / deck chairs area will be expanded somewhat during the rehab.
5 - It would appear that the Trout bar will be remodeled in some way as most of it has been torn down during this construction. It might be due to the remodeled walkway / ADA access may force the Trout Bar to relocate a bit due due the other needs of this renovation.
Finally, in that the footprint of the pool will remain the same, I do not think that the construction will last beyond the end of November. I would really not be surprised to learnt that the pool renovation may actually open earlier than expected. All-in-all, I believe the new splash zone, play area for the kids will be a great addition to the courtyard area.
That is all for now