Of the present
DVC resorts, only OKW was completed in phases. All others were completed at the time they opened. (VB was supposed to have more phases, but that plan was cancelled.)
OKW did sell out originally in summer '98 (?) and then reopened sales when buildings 62-64 were completed in 1999.
Sales for both OKW and BWV ended in fall '00 when sales began for VWL- that resort opened for reservation at the same time.
BWV reopened sales this past spring when they sold the area that has been used for models and offices in the sales center. Those rooms will be available for use after the sales center moves to SSR. Sales originally began in summer, 1996 when the resort opened.
BCV began sales in Feb '02 and opened on July 1, 2002- sales ended there this August.
VWL began sales in fall 2000 and allowed DVC reservations in Feb. 2001. Sales were ended in Feb. 2002 (but reopened last spring until closed again in August)
OKW began sales in Oct. 1991 when the resort opened. The resort was not completed for several years with South Point the last major area to open- around 1994 (?). Sales ended around 1998, but began again in 1999 when the old sales center (Commodore House) was removed and three more buildings built-for the final phase of OKW (This phase was described in the original plans). Sales completed in fall, 2000 when VWL sales began.
HH opened in 1996, but sales began in 1995 and ended this past summer. VB opened in 1995- with saes at the same time and ended just this past summer.
SSR will be a larger resort than any of the others to date- sales began this August and the resort will open next May. Scheduled are 12 buildings. The first four should be completed by late summer, 2004 and then the remainder will open, at a rate of one per month, beginning in 2005. Sales will likely take at least 5-7 years to complete.
Stay Tuned!!