Construction update
Here is the listing of interesting items from paperwork filed with Orange County in the last week:
* Magic Kingdom parking lot milling and overlayment of main entrance and exit roads, east tram lane, Sneezy and Donald parking lots.
* Magic Kingdom milling and overlayment of Park 3 Canal Road.
* Main Entrance/TTC installation of fiber optic cabling and electrical outlets.
* Magic Kingdom Main Street carpentry and electrical work.
* Magic Kingdom Tomorrowland electrical work.
* Magic Kingdom Tomorrowland Terrace Noodle Station modification of existing handrails and installation of new ceiling fans.
* Epcot France pavilion wine shop POS CCTV cameras installation.
* Disney's Hollywood Studios Stage 1 Company Store removal and replacement of 13 windows.
* Disney's Hollywood Studios Oscar's Stroller Rental POS CCTV cameras installation.
* Downtown Disney Team Disney electrical work.
* Grand Floridian Resort building work.
* Contemporary Resort Convention Center loading dock removal of existing sliding door system and replacement with new, high speed and roll-down metal door system.
* Contemporary Resort Convention Center cast parking installation of electrical outlets.
* Wilderness Lodge milling and overlayment of the entrance & exit of the porte cochere and parking lot road.
* Yacht & Beach Club Resorts walkway retaining wall concrete inventory and demolition with installation of new concrete.
* Coronado Springs Resort Dig Site pool building replacement of heat exchanger.
* Pop Century Resort all buildings guest room rehab.
Construction update
Here is the listing of interesting items from paperwork filed with Orange County in the last week:
* Magic Kingdom parking lot milling and overlayment of main entrance and exit roads, east tram lane, Sneezy and Donald parking lots.
* Magic Kingdom milling and overlayment of Park 3 Canal Road.
* Main Entrance/TTC installation of fiber optic cabling and electrical outlets.
* Magic Kingdom Main Street carpentry and electrical work.
* Magic Kingdom Tomorrowland electrical work.
* Magic Kingdom Tomorrowland Terrace Noodle Station modification of existing handrails and installation of new ceiling fans.
* Epcot France pavilion wine shop POS CCTV cameras installation.
* Disney's Hollywood Studios Stage 1 Company Store removal and replacement of 13 windows.
* Disney's Hollywood Studios Oscar's Stroller Rental POS CCTV cameras installation.
* Downtown Disney Team Disney electrical work.
* Grand Floridian Resort building work.
* Contemporary Resort Convention Center loading dock removal of existing sliding door system and replacement with new, high speed and roll-down metal door system.
* Contemporary Resort Convention Center cast parking installation of electrical outlets.
* Wilderness Lodge milling and overlayment of the entrance & exit of the porte cochere and parking lot road.
* Yacht & Beach Club Resorts walkway retaining wall concrete inventory and demolition with installation of new concrete.
* Coronado Springs Resort Dig Site pool building replacement of heat exchanger.
* Pop Century Resort all buildings guest room rehab.