1. All Star Movies currently going through a refurb, about 33% complete.
2. Pop Century currently going through a refurb, about 90% complete.
3. All Star Sports scheduled to start refurb after Pop completes.
4. All Star Music scheduled to begin once Movies completes.
5. Art of Animation is not scheduled as of now.
1. All Star Movies currently going through a refurb, about 33% complete.
2. Pop Century currently going through a refurb, about 90% complete.
3. All Star Sports scheduled to start refurb after Pop completes.
4. All Star Music scheduled to begin once Movies completes.
5. Art of Animation is not scheduled as of now.
Hi there.
Do you have updated refurb info on Movies? I know 9 & 10 are done. I think I read that 7 & 8 are almost done, or completely done? There was a thread somewhere but i cant find it now.
Hi there.
Do you have updated refurb info on Movies? I know 9 & 10 are done. I think I read that 7 & 8 are almost done, or completely done? There was a thread somewhere but i cant find it now.
Pop is taking between 72 and 90-something days per building, with the last building still in progress. Even surprising the smaller AS buildings will take less time, if he shocked if more than one of the ten buildings is completed and occupant-ready in December.