Our home resort is the poly and today we got a letter structural integrity reserve study
I have no clue what all of this is about
The only part I sort of understand is the association collected and has budgeted sufficient reserves

We’ve been members since 2016 and never got anything like this before
It sounds like it’s good news
Thanks
 
A letter dated 05/06/2025 was sent to BCV owners. The letter said that BCV had completed the structural integrity reserve study (SIRS) as required by Florida Statutes 718.112 (2)(g). It said that the result was that the Association has collected and budgeted sufficient reserves to maintain, repair, and replace SIRS components at the resort. It tells you how to make a written request for a copy of the study.

Here is the law:

http://www.leg.state.fl.us/Statutes...ute&URL=0700-0799/0718/Sections/0718.112.html

(g) Structural integrity reserve study.—

1. A residential condominium association must have a structural integrity reserve study completed at least every 10 years after the condominium’s creation for each building on the condominium property that is three stories or higher in height, as determined by the Florida Building Code, which includes, at a minimum, a study of the following items as related to the structural integrity and safety of the building:
a. Roof.
b. Structure, including load-bearing walls and other primary structural members and primary structural systems as those terms are defined in s. 627.706.
c. Fireproofing and fire protection systems.
d. Plumbing.
e. Electrical systems.
f. Waterproofing and exterior painting.
g. Windows and exterior doors.
h. Any other item that has a deferred maintenance expense or replacement cost that exceeds $10,000 and the failure to replace or maintain such item negatively affects the items listed in sub-subparagraphs a.-g., as determined by the visual inspection portion of the structural integrity reserve study.

2. A structural integrity reserve study is based on a visual inspection of the condominium property. A structural integrity reserve study may be performed by any person qualified to perform such study. However, the visual inspection portion of the structural integrity reserve study must be performed or verified by an engineer licensed under chapter 471, an architect licensed under chapter 481, or a person certified as a reserve specialist or professional reserve analyst by the Community Associations Institute or the Association of Professional Reserve Analysts.

3. At a minimum, a structural integrity reserve study must identify each item of the condominium property being visually inspected, state the estimated remaining useful life and the estimated replacement cost or deferred maintenance expense of each item of the condominium property being visually inspected, and provide a reserve funding schedule with a recommended annual reserve amount that achieves the estimated replacement cost or deferred maintenance expense of each item of condominium property being visually inspected by the end of the estimated remaining useful life of the item. The structural integrity reserve study may recommend that reserves do not need to be maintained for any item for which an estimate of useful life and an estimate of replacement cost cannot be determined, or the study may recommend a deferred maintenance expense amount for such item. The structural integrity reserve study may recommend that reserves for replacement costs do not need to be maintained for any item with an estimated remaining useful life of greater than 25 years, but the study may recommend a deferred maintenance expense amount for such item.

4. This paragraph does not apply to buildings less than three stories in height; single-family, two-family, or three-family dwellings with three or fewer habitable stories above ground; any portion or component of a building that has not been submitted to the condominium form of ownership; or any portion or component of a building that is maintained by a party other than the association.

5. Before a developer turns over control of an association to unit owners other than the developer, the developer must have a turnover inspection report in compliance with s. 718.301(4)(p) and (q) for each building on the condominium property that is three stories or higher in height.

6. Associations existing on or before July 1, 2022, which are controlled by unit owners other than the developer, must have a structural integrity reserve study completed by December 31, 2024, for each building on the condominium property that is three stories or higher in height. An association that is required to complete a milestone inspection in accordance with s. 553.899 on or before December 31, 2026, may complete the structural integrity reserve study simultaneously with the milestone inspection. In no event may the structural integrity reserve study be completed after December 31, 2026.

7. If the milestone inspection required by s. 553.899, or an inspection completed for a similar local requirement, was performed within the past 5 years and meets the requirements of this paragraph, such inspection may be used in place of the visual inspection portion of the structural integrity reserve study.

8. If the officers or directors of an association willfully and knowingly fail to complete a structural integrity reserve study pursuant to this paragraph, such failure is a breach of an officer’s and director’s fiduciary relationship to the unit owners under s. 718.111(1).

9. Within 45 days after receiving the structural integrity reserve study, the association must distribute a copy of the study to each unit owner or deliver to each unit owner a notice that the completed study is available for inspection and copying upon a written request. Distribution of a copy of the study or notice must be made by United States mail or personal delivery to the mailing address, property address, or any other address of the owner provided to fulfill the association’s notice requirements under this chapter, or by electronic transmission to the e-mail address or facsimile number provided to fulfill the association’s notice requirements to unit owners who previously consented to receive notice by electronic transmission.

10. Within 45 days after receiving the structural integrity reserve study, the association must provide the division with a statement indicating that the study was completed and that the association provided or made available such study to each unit owner in accordance with this section. The statement must be provided to the division in the manner established by the division using a form posted on the division’s website.
 