they sites in loop 500 is beginning to come to pass. the sites are being made larger and the shell's are going away. they have them formed up and are ready to be be extended,and the golf carts are being moved to the front.
Is the 500 loop closed? If so they are ahead of (or have changed) the original schedule.
Loop 900 closed 7/08 to 7/25 reopens 7/26/08.
Loop 1000 closed 7/27 to 8/08 reopens 8/09/08.
Loop 1100 closed 8/10 to 8/22 reopens 8/23/08.
Loop 500 closed 8/24 to 9/21 reopens 9/22/08.
Anyone been on the 900, 1000 or 1100 loop lately? Have they been completed?
If so, this could answer my big question... Will all sites on a loop be converted to Premium or will premium and preferred be mixed on a loop.
I for one vote for "mixed" as that would mean that fewer sites are premium.
Any one stayed on 1800 or 1900 lately. By the schedule they should have cable and be premium.
The original schedule stated: "The addition of cable TV and Internet will not require any down time but completion dates are as follows:
Loop 300 Already completed
Loop 1900 completed by 7/04/08
Loop 1800 completed by 7/25/08"