I think I read on my facebook link to DCl that the Dream took something like 607 days from first cut to float out .... so I have a question. If they are just now starting to build the Fantasy why is it that it will completed in a shorter amount of time? Isn't the maidne voyage for the Fantasy going to be in 2012 which would make it less than 365 days??
" To answer yesterday's question, 607 days elapsed between the steel-cutting and float-out ceremonies for the Disney Dream. Only 50 days remain before her maiden cruise from Florida's Port Canaveral! Which of our fans will be aboard?
Disney Dream - Disney Cruise Line
Source: fb.disneyparks.com
" To answer yesterday's question, 607 days elapsed between the steel-cutting and float-out ceremonies for the Disney Dream. Only 50 days remain before her maiden cruise from Florida's Port Canaveral! Which of our fans will be aboard?